The residential credit is gone, but businesses can still claim Section 48E — if the system is placed in service by 31 Dec 2027. The deadlines that now apply.
The short answer
Businesses can still claim the federal solar investment credit under Section 48E in 2026, but the timing rules changed. Projects that began construction on or before 4 July 2026 have four calendar years to be placed in service; projects starting after that date must be operating by 31 December 2027 to qualify at all. That is the deadline that matters for any San Diego business starting now — and it is separate from the residential credit, which ended entirely on 31 December 2025.
- The commercial credit under Section 48E survived the One Big Beautiful Bill Act; the residential credit under Section 25D did not
- A project starting construction today must be placed in service by 31 December 2027 to claim it
- Projects that began construction by 4 July 2026 get a four-calendar-year completion window instead
- Systems under 1 MW reach the full rate automatically; larger projects must meet prevailing wage and apprenticeship rules
- Separately, 5-year MACRS depreciation plus 100% bonus depreciation remains available on commercial solar
- Commercial rooftop projects do not use the City's instant residential permit path, so build extra weeks into the schedule
If you own or operate a commercial building in San Diego, the 2026 solar tax credit question has a different answer than the one your residential neighbours got. The 30% residential credit is gone. The commercial credit is not — but it now runs on a clock, and the clock has already ticked past its first checkpoint. This guide sets out which federal credit still applies to business-owned solar, the two deadline paths created by the One Big Beautiful Bill Act, what depreciation still does for the numbers, and the local scheduling realities that decide whether a project makes a placed-in-service deadline. San Diego Solar designs and builds commercial systems across San Diego County with in-house crews, so the timeline advice here comes from the permitting and interconnection side, not the tax side.
This is general information, not tax advice. Credit eligibility, basis and documentation are specific to your entity and your project. Confirm everything below with your CPA or tax counsel before you rely on it.
What this guide covers
- Which federal solar credit businesses can still claim in 2026
- How much the credit is worth, and the 1 MW rule that decides it
- The two deadline paths, and which one applies to you
- What "beginning construction" means, and why that definition is unsettled
- What depreciation still contributes
- What California and San Diego add on top
- Why commercial permitting runs slower than residential here
- What a realistic schedule looks like against a 2027 deadline
Is there still a commercial solar tax credit in 2026?
Yes. The Clean Electricity Investment Credit under Section 48E remains available to business taxpayers for solar property, and it is a genuinely different provision from the residential credit homeowners lost.
The distinction that trips people up: the One Big Beautiful Bill Act, signed 4 July 2025, terminated the Section 25D residential clean energy credit for property placed in service after 31 December 2025, with no phase-down. That is the credit homeowners claimed on their own roofs, and it is finished. Section 48E, which businesses use for commercial-scale property, was tightened rather than terminated — the Act imposed deadlines on it instead of ending it.
So a San Diego business looking at a warehouse roof, a parking canopy or a multi-tenant property in 2026 is working with a live federal credit. A homeowner looking at the same question is not. Different code sections, different outcomes, and a lot of published content still conflates the two.
How much is the commercial solar credit worth?
The headline figure is 30% of eligible project cost — but how you get to 30% depends on system size, and that distinction favours most San Diego commercial rooftops.
Section 48E is structured as a base rate with a multiplier attached to labour standards. Projects that meet prevailing wage and apprenticeship requirements reach the full rate; projects that do not are left at the base. The exception that matters locally: facilities under 1 MW qualify for the full rate automatically, without having to satisfy the prevailing wage and apprenticeship conditions. A typical single-building commercial rooftop in San Diego — a warehouse, a dealership, a medical office, a light-industrial unit — sits well under 1 MW, which means the labour-standards paperwork that dominates utility-scale projects usually does not apply.
Above 1 MW, prevailing wage and apprenticeship compliance becomes a condition of the full rate, and the documentation has to be maintained through construction rather than assembled afterwards. If your project straddles that line, the compliance cost belongs in the model.
There are also bonus adders layered on top of the base credit for things like domestic content and location in a qualifying energy community, and a further category tied to low-income communities. Whether any of them apply to your address and your equipment is a project-specific determination — worth asking your tax adviser to check rather than assuming, because the adders are where the largest variance between two similar projects comes from.
Two things to keep in perspective. First, a credit is only worth what you can use: unused amounts carry forward, but the timing of the benefit depends on your tax position. Second, the credit reduces the basis you depreciate, so the credit and the depreciation interact rather than simply adding together.
What are the two deadline paths for Section 48E?
Two, and which one you are on depends on a single date: whether construction began on or before 4 July 2026.
- Began construction on or before 4 July 2026 — the project has a four-calendar-year window from the year construction began in which to be placed in service. This is the more generous path, and it closed to new entrants on 4 July 2026.
- Begins construction after 4 July 2026 — the project must be placed in service by 31 December 2027 to claim the credit at all. No four-year window, no extension.
For any business starting a project now, the second path is the one that applies. Placed in service, in practical terms, means the system is complete and has permission to operate — not that it is signed, permitted or installed. Utility approval is part of the finish line, and it is the part least under anyone's control.
That leaves roughly sixteen months from the second half of 2026. For a straightforward commercial rooftop that is comfortable. For a project involving a structural upgrade, a service upgrade, a landlord consent process or a significant interconnection study, sixteen months is a real schedule that has to be managed rather than assumed.
What counts as "beginning construction" — and why is the answer unsettled?
Two established methods exist: the physical work test (physical work of a significant nature has begun) and the five percent safe harbour (5% or more of the total project cost has been incurred). Both have long histories in IRS guidance.
The complication is that the rules governing which method you may use have been in flux. IRS Notice 2025-42 limited the five percent safe harbour to solar facilities of 1.5 MW AC or less, effective from 2 September 2025, pushing larger projects to the physical work test only. In June 2026 a federal district court vacated that notice and remanded it to the IRS, which restored the safe harbour — for now, and subject to whatever the agency or an appeal does next.
<!-- UNVERIFIED: OBBBA also added foreign-entity-of-concern "material assistance cost ratio" sourcing rules to 48E. A widely repeated figure is 40% of manufactured-component value, applying to projects beginning construction after 31 Dec 2025, but that specific percentage/date pairing could not be confirmed against a primary source, so it is described qualitatively below rather than quoted. -->
The practical reading for a business owner: do not build a plan around a begin-construction position without your tax counsel involved. If your route to the credit depends on having begun construction by 4 July 2026, the documentation supporting that position matters more than the installation itself. The Act also added sourcing restrictions tied to components from certain foreign entities, which is a documentation burden your tax adviser and your installer both have to satisfy — ask for the component sourcing record as part of the project file, not afterwards.
If your project has not begun, this is simpler: you are on the 31 December 2027 placed-in-service path, and the question becomes a scheduling one rather than a legal one.
What does depreciation still contribute?
More than most business owners expect, and it did not get worse in 2025 — it got better.
Commercial solar is 5-year MACRS property, and the One Big Beautiful Bill Act restored 100% first-year bonus depreciation on a permanent basis for qualified property acquired after 19 January 2025, removing the phase-down schedule that had been stepping it down. For a business with taxable income to shelter, that first-year deduction can matter as much to the cash-flow case as the credit does.
The interaction between credit and basis is exactly the kind of detail to model with your CPA rather than from a blog: the credit reduces depreciable basis in ways that depend on how the project is financed and owned. What is worth taking away is that the commercial case rests on three legs — the credit, the depreciation and the avoided utility cost — and only one of those has a 2027 deadline on it.
What do California and San Diego add on top?
Three things, none of them a cash rebate on the panels themselves.
- Net billing changes what the system should look like. Since 15 April 2023, new California solar customers, commercial included, have taken service on the net billing tariff. Under the CPUC's net-billing rules, exported power is credited at its value to the grid rather than at retail. For a business whose load runs 9 to 5, that is actually less punishing than it is for a household — you consume most of your production as you make it. For a business whose demand peaks in the late afternoon, storage is the lever.
- SGIP for storage. California's Self-Generation Incentive Programme, overseen by the CPUC through California's SGIP programme, includes non-residential budget categories and is administered in SDG&E territory by the Center for Sustainable Energy. Budgets and eligibility tiers shift as funds draw down, and participation carries conditions including enrolment in a qualified demand-response programme — so treat it as a process to start early, not a discount to assume.
- Demand charges. For most commercial SDG&E accounts, the bill is not just energy — it is also a demand charge based on your highest interval of the month. Solar alone shaves energy; solar plus storage can shave the demand peak. That is often where the larger commercial saving sits, and it is invisible if you model only kilowatt-hours.
Our custom and commercial systems page covers how we approach sizing for commercial load profiles, which is a different exercise from residential sizing.
Why does commercial permitting take longer in San Diego?
Because the fast path is residential-only. The City of San Diego self-issues rooftop solar permits with no plan review — but the City's solar permit programme limits that path to single-family homes, duplexes and townhouses, with caps of 38.4 kW AC of generation, a 320-amp service upgrade and 38.4 kWh of storage.
A commercial project sits outside all of that. Expect plan review, and expect the review to touch more disciplines: structural for roof loading, fire access and setbacks, electrical for service capacity, and possibly the tenant improvement process if you are altering a leased space. Add the following where they apply:
- Independent cities — Carlsbad, Chula Vista, Escondido, Oceanside, Poway, Vista, El Cajon, Santee and the others run their own Building Divisions and their own commercial timelines
- Unincorporated addresses — projects in areas such as Fallbrook or Rancho Santa Fe route through County Planning & Development Services
- Coastal zone — a coastal-zone commercial property may involve the local coastal programme and, in some cases, the California Coastal Commission
- Title 24 compliance — the 2025 edition of California's Building Energy Efficiency Standards took effect on 1 January 2026 and applies to non-residential work as well as homes
- Landlord and lease consent — often the longest lead item on a leased building, and one no contractor can accelerate
There is also the roof itself. Putting a 25-year array on a low-slope commercial roof with eight years left in it means paying to remove and reset the array later. Handling the roof and the solar together avoids that and produces one workmanship warranty across the penetrations rather than a dispute between two trades.
What does a realistic schedule look like against the 2027 deadline?
Work backwards from permission to operate, not forwards from signing. The sequence for a commercial project runs roughly:
1. Load analysis and design — twelve months of interval data, not just bill totals, because demand charges hide in the intervals 2. Proposal and approvals — we return a written proposal within 48 hours of having the usage data; your side then needs board, landlord or ownership sign-off 3. Engineering and plan submission — structural and electrical drawings, then the review queue at whichever authority has jurisdiction 4. Interconnection application with SDG&E — filed in parallel, and historically the long pole on commercial projects 5. Construction — the part with the most visible progress and often the least schedule risk 6. Inspection and permission to operate — the actual placed-in-service moment
The lesson from that list is that the parts you control are not the parts that decide the date. If a 31 December 2027 placed-in-service date is load-bearing for your tax position, the usage-data and approvals steps need to start now, because they are the ones that consume months without producing anything visible.
Send us that data and we will return a written proposal within 48 hours, with the permitting path for your specific jurisdiction and a schedule built backwards from permission to operate. Start with a free solar quote, or call San Diego Solar at (619) 514-0095. Then take the numbers to your CPA — the tax position is theirs to confirm, and the schedule is ours.
Frequently asked questions
Did the One Big Beautiful Bill Act eliminate the commercial solar tax credit?
No. It terminated the residential credit under Section 25D for property placed in service after 31 December 2025, and it imposed deadlines on the commercial credit under Section 48E rather than ending it. Businesses starting now must be placed in service by 31 December 2027 to claim it.
Can a landlord claim the credit on a building leased to tenants?
Generally the party that owns the solar property and has the tax basis claims the credit, which is why ownership structure matters more than who occupies the building. Split-incentive situations between landlord and tenant are common and are worth structuring with your tax adviser before design starts.
Does a non-profit or public agency get anything, since it has no tax liability?
Tax-exempt entities have historically accessed value through direct-pay elections or through third-party ownership structures, both of which carry their own rules and deadlines. This is a question for counsel early in the project rather than late, because it affects how the system should be owned.
Is battery storage part of the commercial credit?
Storage is separately eligible property under the current framework, and it also opens the door to SGIP and to demand-charge management. For most commercial San Diego accounts, battery storage is where the demand-charge savings come from rather than from panels alone.
Does my project need to meet prevailing wage rules to get the full credit?
Not if the facility is under 1 MW — those qualify for the full rate automatically. At 1 MW and above, prevailing wage and apprenticeship requirements become a condition of the full rate, and the records supporting compliance have to be kept as the work happens.
How long does a commercial solar project take in San Diego?
Longer than the 6 to 10 weeks a residential project runs, because commercial work goes through plan review rather than the instant residential permit path, and commercial interconnection takes longer. Plan on several months and treat landlord approvals and interval-data collection as the front-loaded risk.
The single most useful thing a San Diego business owner can do this month is pull twelve months of interval data from the SDG&E account — not the bill summaries, the intervals — and look at where the demand peaks land. That data determines system size, whether storage earns its place, and how much of your bill solar can actually reach.